Project Status

In Progress

Duration

96 weeks

Value

£7,000,000

Main Client

Hinguja Group & OHL Desarrollos

Sector

High-End Residence

Services

Mechanical & Electrical

Principal Contractor

Ardmore

MEP Consultant

Aecom

Project Overview

Ardmore have been contracted to convert the Old War Office Building on Whitehall into part hotel and part high end, multi-million pound residential apartments.

Works are progressing well on-site and we are currently coming toward the end of the first phase of first fix electrical works.

The first phase of the second fix is due to start with the continuation of the first fix being on-going.

Project Highlights

  • Co-ordination challenges
  • Specialist high end fixtures and fittings
  • Specialist home automation system
  • Complex work sequencing with other trades